May I ask the coal-fired boiler before the installation of the need for environmental protection department approval, approval of the document basis?
Must be approved before it can be put into use, according to the Environmental Impact Assessment Law of the People's Republic of China
Environmental Impact Assessment Law of the People's Republic of China: New coal-fired heating boilers are prohibited in areas covered by urban central heating pipe networks
Environmental Impact Assessment Law of the People's Republic of China: Boiler Room Project Must Be Conducted first
The EIA includes:
Analysis of environmental rationality of site selection;
Analysis of the production process;
Analysis of major pollutants and emissions to meet standards;
Environmental protection measures;
Total control indicators;
Site selection requirements can not affect environmentally sensitive areas, total control indicators meet the requirements, environmental protection measures effectiveness analysis.
Environmental transformation of boilers in Inner Mongolia
In accordance with the above contents of the EIA approval documents (EIA report, table, registration form), the boiler room can start construction, before the start of operation also need to carry out environmental protection acceptance.
Before the environmental protection procedures are completed, other departments shall not approve the relevant documents, environmental procedures have the right to a veto, but also other relevant approval documents pre-procedures.